SAP PI/PO to SAP Integration Suite migration: a practical playbook

Inventory every PI/PO scenario, run Migration Assessment, and sort each into migrate, redesign or retire. Use the Cloud Integration migration tool where objects are supported, choose cloud or Edge Integration Cell runtime, test with regression packs, and cut over in controlled waves before mainstream maintenance ends on 31 December 2027.

Published 2026-10-06By Spanovix
01Key takeaways

What you will learn

  1. Mainstream maintenance for PI/PO 7.5 ends on 31 December 2027, so the plan must work backwards from that date.
  2. Start with an inventory and Migration Assessment, not with tooling.
  3. Sort every scenario into migrate, redesign or retire before anyone builds anything.
  4. Choose the runtime per scenario: Cloud Integration by default, Edge Integration Cell where data must stay in your landscape.
  5. Treat testing, cutover and monitoring as workstreams with owners, not as the last week of the project.

For CIOs, integration architects and heads of SAP centres of excellence who must move PI/PO workloads to SAP Integration Suite.

02Read the guide

Why the deadline shapes the plan

SAP Process Orchestration 7.5 and PI 7.5 follow the SAP NetWeaver 7.5 maintenance strategy. Mainstream maintenance ends on 31 December 2027. Optional extended maintenance runs until 31 December 2030. Releases below 7.5 are already out of maintenance, so if any part of your estate is still there, it is the first risk to close.

Extended maintenance is optional and should be read as a fallback. A plan that depends on it has no margin left. The sensible approach is to work backwards from 31 December 2027, reserve time at the end for the scenarios that turn out harder than expected, and decide now who owns each decision.

SAP Integration Suite is SAP's strategic integration platform on SAP BTP and the successor path for PI/PO workloads. It is not a single product to install. It is a set of capabilities, and a good migration uses only the ones you need:

  • Cloud Integration for integration flows.
  • API Management for API proxies, policies and a developer portal. It is now offered only as a capability within SAP Integration Suite.
  • Integration Advisor and Trading Partner Management for B2B.
  • Integration Assessment and Migration Assessment for planning.
  • A migration tool in Cloud Integration for supported PI/PO objects.
  • Open Connectors for third-party connectivity.
  • Event-driven integration with SAP Integration Suite, advanced event mesh.

This playbook has seven steps, followed by governance, a real example and a closing checklist.

Step 1: Build the inventory and run the assessment

Do not start with tooling. Start with a complete list of what runs today. Many PI/PO systems hold scenarios that nobody has used for a long time, and many hold scenarios that only one person understands.

What to capture for each scenario

For every interface, record these items:

  • Business purpose and the business owner who can approve a change.
  • Sender and receiver systems, and whether each is on premise, in a cloud or at a partner.
  • Adapters and protocols in use.
  • Mapping logic, including any custom code.
  • Error handling, retries and who is told when something fails.
  • Volume pattern: scheduled batch, on demand, or continuous.
  • Dependencies on other scenarios, such as shared mappings or shared receiver configuration.
  • Whether the scenario is B2B, A2A or an API candidate.

Continue reading

Full guide and PDF

Get the full migration playbook

  • Assessment and wave-planning worksheets you can reuse
  • Cutover and rollback checklists per scenario type
  • Governance model for roles, approvals and support

We use your details to send this and to follow up about it. Nothing else.

03

Questions

When does maintenance for SAP PI/PO end?

SAP Process Orchestration 7.5 and PI 7.5 follow the SAP NetWeaver 7.5 maintenance strategy: mainstream maintenance runs until 31 December 2027, with optional extended maintenance until 31 December 2030. Releases below 7.5 are already out of maintenance. Treat extended maintenance as a fallback, not as the plan.

Is SAP Integration Suite the successor to PI/PO?

Yes. SAP Integration Suite is SAP's strategic integration platform on SAP BTP and the successor path for PI/PO workloads. It combines Cloud Integration, API Management, B2B capabilities such as Integration Advisor and Trading Partner Management, Open Connectors and event-driven integration with advanced event mesh.

Can the migration tool move all my PI/PO content automatically?

No. The migration tool in Cloud Integration moves supported PI/PO objects. Migration Assessment evaluates your existing scenarios and the migration effort. Anything outside the supported set, and anything you decide to improve, has to be redesigned and rebuilt as an integration flow or another suitable pattern.

When should I use Edge Integration Cell instead of Cloud Integration?

Choose Edge Integration Cell when integration flows or API proxies must run in your own landscape, on a customer-managed Kubernetes cluster, while you still design and monitor content in the cloud. Choose standard Cloud Integration when no such constraint exists, because it avoids operating the cluster yourself.

How do I monitor integrations after moving to SAP Integration Suite?

Cloud Integration offers message processing logs, trace and log levels, and a monitor for message status and deployed content. SAP Alert Notification service can raise alerts, and SAP Cloud ALM provides integration and exception monitoring across SAP cloud and on-premise components. Define ownership and runbooks before go-live.